We close on a Des Moines house in three weeks and radon came back high. Is there time?

Direct answer

Usually, yes. A typical install is a one-day job, and quotes can be written within days of the report. The piece to schedule deliberately is Iowa's independent verification test, which comes from someone outside the installer's firm.

More detail

Work the calendar backward. Closing day anchors it; before closing you want the verification report in hand; before the verification test the fan needs to run while the house sits in normal use; before the install comes a written quote based on the actual foundation; and before the quote, someone has to see the house. Three weeks holds all of that comfortably when the first call happens this week, and gets tight when it happens in week two. The Iowa wrinkle helps buyers rather than hurting them: because the installer's firm cannot run the final test, the number you receive at the closing table was not produced by the company the seller hired to install, which is exactly the kind of evidence a lender, an agent, and a buyer can all accept without squinting. Share the purchase deadlines on the first call and the whole sequence gets built backward from closing. Who writes the check is its own negotiation, covered in who pays.

Authoritative sources

Ready to get started?

The Iowa Radon Survey found 71. Mon-Sat 8am-7pm.

Call (515) 642-3364Text us

Prefer to text? Open your texting app